The proposed approach was based on a combination between the theoretical information and practical experience.

back dating contract software issues-34

The different methods that are used to prove delays, as explained in industry standards and handbooks, are theoretical and could be applied in the small simple projects with few numbers of activities but the same methods cannot easily be applied on mega/complex projects.

Proving delays in mega/complex projects, whose schedules contain thousands of activities with many interfaces and lot of causes for delay and disruption is a complicated process and involves lots of details.

When any degree of complexity in the project is examined, it becomes more difficult for the project team to record the delays and disruption events properly because they are always busy dealing with the site issues and other project pressures.

In order for the contractors to be successful, a time extension claim or disruption claims should adequately establish causation and liability and assist in demonstrating the extend of time-related damages experienced as a direct result of the delay events relied upon.

Normally, preparation of the baseline programme starts with the identification of the activities required to execute the work in accordance with the project work breakdown structure and contract plan and specification.

Any project faces delays and disruptions especially the mega/complex projects of today, with many interfaces.

Proving delay and/or disruption is not an easy task and it is a time consuming process especially in the mega/complex projects with thousands of activities, lots of details and interfaces with the involvement of many stakeholders.

It is essential for the project management team to carry out the following pre-planning tasks once the project is awarded: Based on the pre-planning tasks defined above, the contractor can produce an accurate baseline programme which is considered the solid base for any future claim.

Baseline programme represents the contractor’s approach to execute the contract scope prior to the project commencement date showing the planned productivity rates for all types of work which is considered also the non-impacted benchmark for any future claim.

The process of recording the delays and disruption is a dynamic process and needs continuous involvement from the planning team with the support from all other departments.

A practical approach that is recommended to be followed to enable the contractor to prove the delays and build a well-supported claim for extension of time is introduced.